Saltaire Station

Saltaire Station Platform Extension Project

The team at True North Rail using their Truesight™ platform worked in conjunction with North South Rail & Network Rail in order to assist with Signal Sighting requirements to avoid costly data changes to a new Signalling Control System.

TrueSight™ PROJECT

Saltaire Truesight 76m Approach to Station

Overview

Saltaire station is on the Airedale line between Bradord and Leeds and Skipton. It is a busy commuter station both for passengers travelling to Leeds & Bradford and for staff in companies based in Salt’s Mill, as well as serving tourists visiting UNESCO World Heritage Site at Saltaire.

​

The team at True North Rail were called upon to assist with Signal Sighting requirements in order to avoid the need for a costly data change to a new Signalling Control System.

Saltaire Truesight 15m Approach to Station

Curved Section of Railway

Saltaire station is located on a very curved section of railway, and was facing a significant cost impact due to the perceived need to relocate a Signal several hundred meters onto a straighter section of track; a location not preferred by Railway Undertaking representatives. This relocation would also have required a data change for the new Control Centre Signaller Workstation, leading to substantial project costs.

North South Rail logo

Our Role

​True North Rail deployed its advanced gaming engine platform, TrueSight™, to provide an innovative and cost-effective solution. Our team utilised client BIM data and various GIS datasets to create a photorealistic Signal Sighting model using Unreal Engine. This model allowed for rapid review and adjustment of multiple Signalling options in real-time.

​

​

​

Saltaire Truesight Modelling of Man at Station

Key Actions

1. Rapid Implementation: Our Signal Sighting model delivered within 10 days from the client's purchase order, allowing for swift review and decision-making by the Signal Sighting Committee.

​

2. Signal Placement: Our TrueSight™ modelling tools enabled the Signal Sighting committee to quickly visualise and test options and demonstrate that a cantilevered Main Signal positioned to the right, combined with a high-up, reduced offset Banner Repeater would provide a compliant solution. This allowed for the Signal to be repositioned at the end of the new 43m platform extension on the curved section of track and avoid a costly data change to the Signalling Control System.

Truesight logo

Leveraging TrueSight™

3. Dispatcher Visibility: Our TrueSight™ platform provided a realistic dispatchers eye view for the Sighting of OFF Indicators on both platforms, ensuring the optimal Signal/Passenger Train interface arrangements.

​

True North Rail unblocked the signal sighting problem, avoiding any significant cost and programme impacts, whilst also ensuring compliance with Signal Sighting standards. The entire review process was conducted during a 2-hour Teams meeting with the Signal Sighting Committee and other project Stakeholders, showcasing the efficiency and effectiveness of the TrueSight™ tool.

Network Rail

Project Success

The Saltaire Station platform extension project demonstrates True North Rail's commitment to innovation, efficiency, and cost-effectiveness. The successful application of the TrueSight™ platform not only provided a compliant solution but also significantly reduced project costs and timeframes. True North Rail continues to set new standards in the Rail Engineering sector, delivering best-in-class solutions for complex Signalling challenges.

​